to the Delhi to Courtland watermain.
I am writing to you
today to thank you and to praise your production plant employees.
During the winter months of January and February we installed 14,000
metres of 300mm DR18 watermain. The installation by two of our crews
was completed in March. Swabbing was conducted immediately following
that, and within 10 days the hydrostatic pressure testing was passed.
Forty separate sections with absolutely no pressure loss in 2184
joints. Next, a battery of 156 water samples were taken in 39
separate sections. All bacterial tests were negative with only the
last sample at the end of pipeline resulted in elevated background.
Four additional samples were taken and passed in the next two days.
It goes without
saying how well this project went and reflects the high quality of
your product, materials, and people.
We are looking
forward to our next project together on the Beaverdale Road Watermain,
Region of Waterloo.